The project being carried out by Pseudox Explome Tanzania Limited at the Buckreef Gold Mine in Geita has reached 70%. The planned ground magnetic survey covered 800 kilometers, and so far 560 kilometers have been completed.

The project being carried out by Pseudox Explome Tanzania Limited at the North Mara Gold Mine - BARRICK in Nyamongo Tarime has reached 65%. The planned survey was covered 400 kilometers, and so far 260 kilometers have been completed.

We use the latest technologies and techniques to optimize exploration and production, and we work closely with our clients to ensure their specific needs are met.

Drilling setting to a new hole at Mabruki Gold Project in Mbangala, Songwe District.
The project being carried out by Pseudox Explome Tanzania Limited and keeping going on